Report to guide flooding solutions for Monaghan Town

“There seems a perception among the public that the local authority isn’t doing anything about the flooding problems in Monaghan Town, but the opposite is the case,” stated the Cathaoirleach, Cllr Alan Johnston (FG) at Monday’s meeting of the Monaghan Municipal District.

The Cathaoirleach was welcoming news that a draft hydrology report on the causes and possible solutions to the flooding, which disrupts pedestrian and traffic flow in the town centre at times of severe rainfall, has been received by the local authority and is currently being reviewed.

The update came as heavy rain was forecast to fall that evening and over the coming days.

Cllr Johnston said the report will facilitate discussions on how the town flooding can be alleviated. Referring to the complexity of the issue, he said if the solution was simple it would already have been applied. The problem arises in large part from the inability of water to escape quickly enough when there are “deluges” of rain.

MD Co-ordinator Martin Taylor reported that the final version of the hydrology study will be complete by the end of November. “Once finalised, a presentation to the members on the findings and recommendations will be arranged,” he stated.

He said the study’s next stage will focus on the proposed culvert works extending from the ALDI premises to the rear of the Monaghan Credit Union building at Castle Meadow Court, and will also incorporate designs for other potential mitigation measures.

In 2027, Mr Taylor added, tender documentation for the proposed culvert project will be updated using the hydrology consultants’ recommendations. This will allow the tender process to proceed during 2027 with construction likely to commence in 2028 “subject to approvals and funding”.

The co-ordinator also pointed out that the MD has a contractor currently carrying out clearing of vegetation and debris along the Shambles River from Old Cross Square to Tullyherim Bridge, work expected to finish at the end of this month. He said the Department of Climate, Energy and Environment has granted a derogation to allow the operation outside the permitted season for instream river works.

A progress report on the Shambles River project had been requested by Cllr Raymond Aughey (FF), who said this work will ultimately help with flood mitigation in the town centre.

THE BLACKWATER

Cllr Bronagh McAree (SF) proposed at the meeting that correspondence be sent to the Office of Public Works requesting an urgent inspection and maintenance of all drainage channels and watercourses in the MD under its responsibility, particularly along the Blackwater River in the Emyvale area, to ensure they are clear of obstructions and functioning effectively to reduce the risk of recurring flooding there.

The proposal, seconded by Cllr Pauric Clerkin (FG) and adopted, also called on the OPW to provide details of its maintenance programme for the Emyvale Blackwater and a timeline for any necessary works.