Councils meet Eirgrid and ESB over compliance

Officials from Eirgrid and ESB have met representatives of three county councils to discuss compliance and regulatory matters surrounding the controversial North-South Interconnector, as the project edges closer to construction.

A key issue is the formal discharge of pre-commencement planning conditions.

Eirgrid is required to provide detailed documentation to the relevant planning authorities, including Construction Environmental Management Plans (CEMP), Traffic Management Plans (TMP) and Residue Waste Management Plans (RWMP).

Additional roads-related compliance submissions must also address requirements surrounding transport arrangements, road safety and the storage of construction materials and equipment.

The matter was raised at the November monthly meeting of Cavan County Council, where Fianna Fáil councillor Clifford Kelly questioned how Eirgrid and ESB could continue with the project in the face of such significant local opposition.

Cllr Kelly said he “can’t understand” how the current process is continuing, particularly given the strength of feeling among communities opposed to the overheading of the cross-border electricity link. The proposed 138-kilometre overhead electricity route linking County Meath with County Tyrone through Cavan and Monaghan has seen campaigners and landowners spend almost 20 years fighting to have the 400kvw power lines placed underground.

Director of Services Brendan Jennings confirmed the meetings had taken place, noting that the three councils had applied for “further information” on compliance before allowing any more progress.

It follows too the recent appointment by Eirgrid of a dedicated project co-ordinator.

* This article was published with support from the Local Democracy Reporting Scheme