Roadwork delays dominate 2027 budget discussions

Rising construction costs, delays to roadworks and pressure on Local Improvement Scheme (LIS) funding was the focus of the recent Ballyjamesduff Municipal District (MD) budget meeting.

Opening the discussion, Director of Services Lynda McGavigan explained that most of the budget remained largely unchanged from 2026, with the main adjustment relating to discretionary amenity funding.

The allocation is proposed to increase by €2,000 to €169,880.

Noel Connell (SF) welcomed the increase, describing it as positive, although he acknowledged that members would always like to see more funding available.

Attention turned to the roads programme, with Area Engineer John McGahern confirming that industrial action had affected the delivery of works.

“We were planning to start with that about a month and a half ago, but we've been on work-to-rule since,” he explained.

He said there is already a backlog, with contractors also working in other counties, but indicated that work would progress once the strike action is lifted.

Private lanes

However, the difficulties surrounding the Local Improvement Scheme prompted particular concern, with three projects in Murmod, Kilnaleck and Arva facing delays.

Mr McGahern explained that the council had secured a one-week extension from the Department of Rural and Community Development, leaving just eight days to complete the outstanding works.

“We've eight days. I don't know how I'm supposed to get three lanes ready, get them surfaced and get them invoiced in eight days,” he said.

He also rejected suggestions that there was unspent funding available, explaining that inflation had significantly increased the cost of delivering the projects.

The roads programme had cost approximately 10% more than anticipated due to supplier price increases, while the cost of LIS works had risen by around 40% compared with initial estimates.

“The Department doesn't recognise inflation; to them it doesn't exist,” the engineer remarked.

He warned that completing all three projects would require the council to use its own resources to cover the additional costs on private lanes, potentially diverting money from publicly maintained roads.

In the circumstances, he said funding was available for only two of the three projects.

The level of household contributions towards LIS works also came under scrutiny. Cllr T.P. O'Reilly (FG) questioned whether the current €1,200 contribution was sufficient. "You wouldn't tar this table with €1,200," he remarked, suggesting that a higher figure could ensure applicants were genuinely committed to completing their projects.

Cllr Winston Bennett (FG) recalled that contributions had previously been 15% of the costs, questioning why they had subsequently returned to €1,200. He acknowledged that the reduction had been intended to allow more people to access the scheme, but said there was little point creating a lengthy list of applicants if the necessary funding was unavailable.

* This article was published with support from the Local Democracy Reporting Scheme