CMETB school building projects progress report
THE November meeting of the Cavan Monaghan Education and Training Board (CMETB) was updated on the progress of various school building projects.
BEECH HILL COLLEGE
Director of Organisation Support and Development, Karen McBride, delivered the update showing board members a photograph from the day before the meeting, which showed the first floor of the new Beech Hill College extension “100% complete”.
Builders are now moving up to the second floor, the director said.
The development will provide six new general classrooms, four SET rooms, a multimedia room, a specialist construction studies/material technology facility, two science laboratories and dedicated SEN accommodation.
Since work commenced on site in October 2025, the project has reached significant stages, including completion of the ground floor and first-floor slab installation, first-floor steel reinforcement, beam construction and structural steelwork. Cavity insulation is approximately 70% complete, while masonry works are continuing.
CASTLEBLAYNEY COLLEGE
When it comes to Castleblayney College, Ms McBride said CMETB is waiting on the Department of Education’s technical team to visit the school which means, “We are at the mercy of the Department.”
The project is an extension to include a new three-class SEN base and repurposing of existing SEN accommodation.
Karen McBride told the Board she makes “weekly calls” to the Department of Education ensuring the Castleblayney College project remains a priority.
VIRGINIA COLLEGE
Plans for a major extension at Virginia College are moving forward, with the project receiving Department approval to proceed to Stage 2b of the development process.
The proposed extension will deliver nine new general classrooms, two SET rooms, three science laboratories with two preparation areas, an art room, a music room, and a four-classroom SEN base.
INVER COLLEGE
The Department of Education has now completed surveys of the 1950s building at Inver College, which is due for demolition, Ms McBride reported to the November CMETB meeting.
She made the comments following a “very positive” site meeting at the school with the Department of Education and Youth in September.
Plans for a 2,696 square metre two-storey extension for Inver College, which will include a special education needs unit, four specialist classrooms, two SET rooms and a large general-purpose hall, are at the detailed design stage.
Planning permission for the extension was granted by Monaghan County Council in 2024.
Director of Organisation Support and Development, Karen McBride, said following the meeting with the Department, it has been agreed that “minor works” will be carried out on the roof of the so-called 1959 building and some improvement works to be carried out on the 1999 building.
Wear and tear in the roof has caused leaks so that during wet weather staff have to collect rainwater in buckets.
“My heart was in my mouth when you mentioned minor works,” Cllr Colm Carthy, who is chair of the Board of Management at Inver College remarked.
He has been raising the delays to the construction of the extension with the education board regularly.
Relieved that the ‘minor works’ are a temporary measure until demolition of the building begins, Cllr Carthy said: “I do give out every month – and I’ve a right to do so.
“But on behalf of the school’s Board of Management I do have to mention the work that Karen and the management of the school are doing in the background.”
COLÁISTE DÚN AN RÍ
The proposed new development for Coláiste Dún an Rí continues to advance through the planning process, with the Detailed Design Report (Stage 2b) submitted to the Department.
The project will deliver a substantial expansion of the school's facilities, including 23 general classrooms, a two-classroom SEN base, five SET/pastoral support rooms, a multimedia room, specialist rooms for DCG, Home Economics, Art, Construction Studies and Engineering, three science laboratories with two preparation areas, a technology preparation room, three project stores, a staff room and a general purpose/dining area.
BREIFNE COLLEGE
The planned extension at Breifne College continues to progress through the design phase, with the project team currently preparing the Stage 2b Detailed Design Report, which is expected to be finalised in the second quarter of 2027.
The development will deliver a significant upgrade to the school's learning and support facilities, including four general classrooms, seven SET rooms, three science laboratories with two preparation rooms, two engineering rooms, two technology rooms with accompanying preparation areas, a graphics room, an art room, a textiles room, five project stores, and a two-classroom SEN base with ancillary accommodation.